Tuesday, July 15, 2014

Footings Poured - Part 2

It's Day 16 and the footings are completed. The footings were poured on Friday and left in the forms until Monday. The foundation guys then removed the forms and used a saw to clean up areas that spilled through the forms to make clean edges for the drain tile . The drain tile allows water underneath and around the house to move away from the house (but that will come later).

Here's some highlights:




The forms for the poured walls were delivered today.

Bleeder... allows drain tile to exit underneath foundation.

Critter footprints, so funny!


Overall picture of our footings!

Next Up:  The wall forms should be setup tomorrow and the walls may be poured this week if all goes well!