Wednesday, October 29, 2014
Day 122 - Electrical box installed
Today the electrical meter box was installed at the house. Leave it to john to get the commercial grade box for our home. Today our front door was delivered as well. The white construction door will be used until we are ready to install the finished door, this protects our door from the construction activity.
Monday, October 27, 2014
Day 120 - Windows in!
Last Thursday (Day 116) the windows were finally installed. The carpentry crew finished up the final details by Friday (Day 117). The roofer came over the weekend and finished most of the house roof. He will come back next weekend to finish the garage roofing.
Front of house...
Back view...
Living Room...
Garage arches...
Basement Drain Tile...
Sump system complete...
Sump basin working...
Front door...
Garage territory
Wednesday, October 15, 2014
Day 109 - Rainy Weather
It's day 109 and all this week has brought so far is rain! The past Sunday the roofing crew finished a good portion of the roof.
John and I began the drain tile in the basement so we spent the weekend full of mud!
Carpenters should be coming on Monday to finish setting our lovely windows!
Friday, October 10, 2014
Day 104 - Roofing Material Delivered
It's day 104 and our roofing material was delivered to the lot. Tomorrow the crew will come to begin the roof while we begin the drain tile for the basement.
Roofing materials delivered on the roof, of course...
Day 101 - Roofing Chosen
It's day 101 and we decided on our roofing shingles. Roofing material should be delivered Friday and our roofing crew will begin work on Saturday.
Sunday, October 5, 2014
Day 99 - Beginning of Windows
It's day 99 and the crew began this past Friday by installing the windows. Unfortunately, bad weather came and they were only able to start on one window.
The sun came out today and hopefully the weather holds out tomorrow so the crew can finish the windows.
Thursday, October 2, 2014
Day 96 - Framing Finishes
It's day 96 and the crew completed the staircases for the garage to basement, garage to bonus room and first floor to basement stairs. The crew also completed the floor for the bonus room and began the arches for the entry ways.
Windows were delivered today...
Bonus room staircase...
Bonus room...
One of the arches...
Basement staircase on right with temporary railing...
Wednesday, October 1, 2014
Day 95 - Finishing Touches to Rough Framing
It's day 95 and the carpentry crew worked on finishing the hand framing required in the master bedroom and dining room. They also started building the stairs for the basement and removed the 2x4's from each doorway.
Here are parts of the basement staircase which leads to the first floor...
Here is the framing of our double stepped ceiling in the living room...
Master closet :)
View of foyer and office...
Tomorrow our windows will be delivered to the lot and if the weather holds, the crew will start installing on Friday.
Day 94 - Roof Deck Complete
Today the carpentry crew finished the roof deck and started some interior rough finishing.
Sue and Cathy stopped by...
Peak of the bonus room...
Here is a peak of the holes for the roof vents...
Inside view of roof sheathing...