Truck 1...
Tuesday, December 30, 2014
Day 184 - Garage Floor Poured
Day 184 and the garage floor has been poured. Although it's very cold outside, we are heating the garage so the cement cures appropriately. The first cement truck showed up about 9:30am and the entire job took about one and a half trucks.
Monday, December 29, 2014
Day 183 - Moving Slowly
It's day 183 and john and I are on break from work. We are prepping the garage and basement for the floors to be poured soon. We ordered our fireplace and the rough mechanical work has been started.
Here is one shot of the basement plumbing under the floor...
Roof work is almost complete...
Stay tuned for cement pics soon!